Planning Templates · 90-Day Projects
Weekly Capacity Budget: Turn Available Hours into Sprint Commitments
A sprint commitment should fit the hours your team can protect, not the hours a calendar appears to contain. Start with a 40-hour week, subtract 12 hours of recurring meetings and routine duties, and budget from the remaining 28—while keeping part of that time unpromised for interruptions.
That small distinction can keep a 90-day project from becoming a weekly exercise in apologizing for work that was never realistically schedulable. A capacity budget gives each person a clear, repeatable way to show what they can take on, what they have already promised, and what must move when something urgent arrives.
What a weekly capacity budget does
A weekly capacity budget is a short accounting of the hours available for planned sprint work after recurring responsibilities are removed. It turns “I think I can do that” into a commitment tied to time, ownership, and a specific output.
It is not a timesheet, a measure of dedication, or a demand that every hour be filled. The point is to make constraints visible before the team agrees to the work. Meetings, customer support, operational duties, leave, and on-call coverage all take real capacity, even when they do not appear in a project plan.
Think of the budget as a weekly control panel for a longer 90-day effort. The project may have a fixed outcome and a sequence of milestones, but the amount of work a team can safely promise can change from Monday to Monday. A capacity budget makes that change manageable instead of hidden.
Calculate net available hours first
Use a simple calculation for each person:
Net hours for sprint work = contracted weekly hours − standing commitments − known absences
For example, a person working a 40-hour week may have 12 hours of standing commitments: recurring meetings, routine administration, and support coverage. That leaves 28 hours potentially available for planned sprint work. But “potentially available” is not the same as “safe to commit.” The team should reserve some of those hours for unpredictable work.
If this person keeps a 4-hour interruption reserve, the planned-work ceiling becomes 24 hours. That is the number to use when assigning sprint tasks—not 40, and not even the full 28. The reserve is a deliberate part of the plan, not spare capacity waiting to be filled.
| Capacity item | Hours | How to count it |
|---|---|---|
| Weekly working hours | 40 | Start with the person’s actual scheduled workweek. |
| Standing meetings and routine work | −12 | Include recurring duties that cannot simply be dropped for the sprint. |
| Net capacity before reserve | 28 | This is the upper boundary for sprint work plus flexibility. |
| Interruption reserve | −4 | Protect time for urgent requests, overruns, and small surprises. |
| Maximum planned sprint work | 24 | Use this figure when making weekly commitments. |
These numbers are an example, not a universal staffing formula. A customer-facing role with frequent escalations may need a larger reserve. A week with a company-wide planning event may have fewer hours available than a normal week. Use observed work patterns rather than an idealized schedule.
Build the weekly capacity table
Keep the working table small enough to review in a few minutes. Each row represents one person for one week. “Planned work” should describe the activity or task, while “committed output” names something observable that the person expects to complete. This makes the difference between effort and delivery explicit.
| Week | Owner | Net hours | Planned work | Reserve hours | Committed output | Status / change |
|---|---|---|---|---|---|---|
| 1 | Owner name | 28 | Draft onboarding flow; review feedback | 4 | Reviewed draft with agreed feedback recorded | Not started |
| 1 | Owner name | 20 | Prepare test cases | 3 | Test cases ready for team review | Not started |
| 2 | Owner name | 24 | Resolve priority defects | 4 | Agreed priority defects verified or explicitly deferred | Update after Monday check |
Do not treat the sample outputs as a promise that a task will take exactly the listed hours. Capacity is a planning boundary, not a stopwatch. The table helps the team compare the size of the proposed work with the time actually available and make a conscious trade-off when the two do not match.
For a team, calculate capacity person by person before adding it together. Five people with 20 available hours each do not necessarily provide 100 interchangeable hours: skills, approvals, handoffs, and part-time availability affect who can do what. Keep named owners on the work rather than using one large team-wide number that hides bottlenecks.
Set the reserve before choosing the workload
Reserve time works best when the team agrees on its purpose in advance. It can absorb urgent support requests, a short-notice review, or a task that takes longer than expected. If the reserve is repeatedly consumed by the same predictable obligation, that obligation belongs in the standing-commitment calculation instead.
There is no single reserve percentage that fits every team. Begin with recent evidence: look at the last four to six weeks and estimate how much time was spent on genuinely unplanned work. If it averaged three hours a week, a three-hour reserve is a better starting point than an arbitrary rule. Revisit the number when the work pattern changes.
Make one distinction explicit: planned routine work is not an interruption. A weekly support rotation, regular one-to-ones, and an established reporting duty should be subtracted before the reserve is set. Otherwise the same hours are counted twice—or the reserve becomes a vague catch-all for commitments nobody has named.
- Standing commitment: recurring work that is expected and scheduled, such as a weekly team meeting.
- Known absence: leave, training, a public holiday, or a scheduled appointment during the workweek.
- Reserve: protected time for work that cannot be predicted precisely but is likely to arise.
- Planned sprint work: tasks the team actively chooses to deliver during the week.
Make a weekly commitment in four steps
- List the week’s fixed obligations. Each owner records meetings, routine responsibilities, coverage, and known absences. Use the actual calendar for that week rather than copying a standard week without checking.
- Calculate net hours and protect reserve. Subtract fixed obligations from working hours, then set aside the agreed reserve. If the result is unusually low, flag it before selecting tasks.
- Select work up to the planned-work ceiling. Choose the highest-priority items that fit the available hours and the owner’s skills. Name the output and any dependency that could block it.
- Reconcile the budget at the end of the week. Compare the original plan with what happened. Record a short reason for meaningful differences, then use that information to make the next estimate more credible.
A weekly check-in can be brief. The useful questions are practical: Did the reserve cover interruptions? Did planned work fit? What has changed for next week? Is any commitment dependent on a decision or handoff that has not happened yet?
What to do when urgent work takes six hours
Suppose an urgent customer issue takes six hours from an owner who had committed to 24 hours of sprint work. Do not leave the 24-hour commitment untouched and ask the person to absorb the difference after hours. Recalculate the budget and remove or defer six hours of planned work—or agree on a smaller, specific adjustment if some work can be reduced.
Update the table as soon as the change is understood. Mark the urgent item, record the hours it consumed, identify which planned output moved, and name the person who needs to know. If the team cannot tell which work should be displaced, the priority decision is still unresolved; the individual should not be expected to settle it silently.
For example, a 24-hour plan might include a 10-hour draft, an 8-hour prototype change, and a 6-hour review package. If the urgent issue takes six hours, the team could defer the review package and protect the draft and prototype work. Or it might deliver a smaller prototype and retain the review. The right choice depends on the sprint’s priorities, but the cost should be visible.
A reserve exists to soften this kind of disruption. If the six-hour issue exceeds a four-hour reserve, two hours of planned work still need to move. If the reserve is not used, it may be available for a priority item late in the week—but it should not be pre-spent on extra commitments at the start of Monday.
Place the budget across a 90-day cycle
A 90-day project often spans about 13 weeks, but the calendar does not create 13 identical workweeks. Holidays, release dates, travel, and milestone reviews change capacity. Set an initial direction for the full cycle, then make detailed commitments one week at a time.
| Cycle window | Capacity-budget action | Checkpoint |
|---|---|---|
| Weeks 1–2 | Measure recurring commitments and establish a realistic reserve. | Compare estimated availability with actual time spent on unplanned work. |
| Weeks 3–5 | Use the weekly table to commit to the first substantial delivery sequence. | Check whether work is finishing at the expected rate and identify bottlenecks. |
| Week 6 or 7 | Recalculate for the middle of the cycle; account for changed roles, leave, or operational load. | Decide whether scope, sequencing, or ownership needs to change. |
| Weeks 8–11 | Budget around delivery, testing, review, and dependencies—not only production work. | Protect time for validation and fixes instead of spending every hour on new features. |
| Weeks 12–13 | Reserve capacity for acceptance, handoff, documentation, and unresolved priority work. | Confirm what is complete, what is deferred, and what should enter the next cycle. |
The weekly budget is not a replacement for milestone planning. It answers a narrower question: given this week’s real availability, what work can this owner reasonably commit to? Milestones remain useful for setting direction; the budget supplies a grounded view of near-term execution.
Common capacity-planning mistakes
- Budgeting against the full workweek. Forty scheduled hours do not mean 40 hours of project capacity. Subtract recurring duties first.
- Counting the reserve as available for new work. If the team assigns all net hours, the reserve exists only on paper. Keep it separate in the table.
- Using one average for everyone. People have different hours, responsibilities, and constraints. Calculate individual availability before considering team totals.
- Leaving work vague. “Help with launch” cannot be checked reliably. Name an output, such as “review the launch checklist and record unresolved items.”
- Allowing urgent work to become invisible overtime. When new work arrives, show what it displaces and let the appropriate owner make the priority call.
- Never updating the estimate. A budget based on a quiet month may not fit a release week. Recalculate when the workload or calendar changes.
A short weekly review that improves the next budget
At the end of each week, compare the budget with what actually happened. A few notes are enough; the goal is to improve planning, not produce a forensic account of every hour.
- How many hours were available after fixed commitments?
- How much reserve was used, and what used it?
- Which committed outputs were completed, reduced, or deferred?
- Did a dependency, approval, or handoff consume time that was not included?
- What should change in next week’s capacity estimate or priority list?
Repeated misses often point to a planning assumption that needs attention. If the same recurring support task consumes five hours each week, it is no longer an unexpected interruption. If a task regularly waits two days for review, the bottleneck may be reviewer availability rather than the owner’s production capacity. Use the record to correct the model, not to label a person as unreliable.
Keep the system lightweight
The table should make commitments clearer, not add a second job. A spreadsheet, shared document, or existing project tool is enough if the team can see the same fields and update them without friction. Use hours for capacity because they make availability concrete; use outputs for commitments because they make progress understandable.
Start with one week of honest numbers. For a 40-hour schedule with 12 hours of fixed duties and a 4-hour reserve, that means a maximum of 24 planned sprint hours. Review what happened, adjust the reserve if evidence supports it, and repeat. Over a 90-day cycle, that steady recalibration is more useful than a perfect-looking plan made once and ignored.
Frequently asked questions
Should the capacity table include every task?
Include the work that affects the sprint commitment and the fixed duties needed to calculate availability. Break planned work into enough detail to identify an owner and a checkable output, but do not turn the table into an exhaustive minute-by-minute schedule.
What if a person has no predictable weekly schedule?
Budget from the calendar and known duties for the upcoming week, then use a conservative reserve based on recent experience. If availability changes daily, update the table when a material change occurs rather than relying on a stale weekly estimate.
Is reserve time wasted when no urgent issue arrives?
No. It protects the commitment from normal uncertainty. If the reserve remains unused, the team can decide later whether to pull forward a priority item. Keeping it unassigned at the start of the week is what makes it a reserve.